Progress is being made as the sheetrock crew finished up putting up the boards. Yesterday the crew came and put up the drywall corner beads and today the mudding begins.
While on the outside, this past weekend the second set of columns on the vestibule were finally added and we did some dirt moving.
Thursday, July 21, 2011
Thursday, July 14, 2011
Drywall Continues
Day 3 of the Drywall saw the work on the main floor completed as well as the stairwell. Quite a different look at the stairs. The crew moved to the processing facility in the basement and got quite a bit done in the basement. Things are moving along.
Here is the main level - It was getting dark when I shot the photos.
Here are some vineyard shots with the beautiful full moon.
Here is the main level - It was getting dark when I shot the photos.
The basement ceiling/soffit work begins.
This is Richard's wine lab.
Here are some vineyard shots with the beautiful full moon.
Wednesday, July 13, 2011
Sunday, July 10, 2011
Ready for Drywall!!
The July 4th 3 day holiday weekend saw us working long days trying to get the insulation completed. After working 8a til around 10p each day we were able to complete the insulation and get it inspected last week. This weekend we finished up some items (fireplace framing, running phone wire, TV wire, to name a few) so that we are now ready for the drywallers to arrive. At last!! The sheet rock arrived on Friday and the drywallers are scheduled to start either Monday or Tuesday. Then big changes will appear!!
Insulation in the processing area - That was a long way up
Insulation in the processing area - That was a long way up
The fireplace is all framed in.
Cathedral Ceiling Insulation
North wall of tasting room overlooking processing facility - only upper part of wall is an outside wall and needed insulation.
Rocky needed a rest after working so hard